BOSTON-  MassDOT’s Callahan Tunnel Project begins with a full tunnel closure for rehabilitation on December 27, 2013 through March 12, 2014. The Callahan Tunnel Project web page now includes detour maps.  The detour routes were carefully developed by the project team with input from stakeholders.

View directions and detour maps for travel from:

 

View Directions from:

 

Vehicles heading to points south via I-93 Southbound may want to avoid traffic detoured onto Albany Street. MassDOT has opened up access to an express route to I-93 to all vehicles, regardless of occupancy.

 

MassDOT has made improvements to signal timing along detour routes as-needed to facilitate the flow of traffic during construction. Key intersections will be monitored during the tunnel closure by traffic engineers and police. 

The web page also includes trip planning tools during the duration of the closure and a one-page Printable Fact Sheet also translated into Chinese, Portuguese and Spanish

The $34.9 million project includes rehabilitation of the 52-year old tunnel’s deck, curb line, gutters and replacement of the tunnel’s wall panels.  The original deteriorated wall panels were removed in December 2012 as a safety measure due to significant corrosion to the panel wall anchor system.

The proposed work schedule includes the full tunnel closure in early 2014 with detours in place, followed by an additional 4-5 months of work requiring overnight closures between 11p.m. and 5a.m. The complete closure of the tunnel will reduce the overall duration of the project, provide enhanced public safety by minimizing changes to traffic flow, and better coordinate with other local projects including Tobin Bridge work, which is scheduled to resume in spring 2014.

For project details, visit: www.mass.gov/massdot/CallahanTunnelRehab

To sign up for the project email list or communicate with the project team, email: callahan.tunnel@state.ma.us

In 2009, the Massachusetts Department of Transportation (MassDOT) was created to unify the state’s various transportation agencies. MassDOT now includes the Highway division, the MBTA and Mass Transit, Aeronautics, and the Registry of Motor Vehicles.  MassDOT is committed to providing a safe and reliable transportation system to all those who travel in the Commonwealth and works to deliver excellent customer service. MassDOT has been nationally recognized for its innovative approach to transportation, including the Accelerated Bridge Program, the “Where’s My Bus and Train?” apps and “Fast 14” work.  For more information, visit MassDOT at our website: www.mass.gov/massdot.

 

####

Translation Disabled  | Translation Support